Monday, 27 October 2008

Downstairs toilet fitted

On friday the new downstairs toilet arrived. I dont think Ill be using it though

Windows in

Wednesday, 22 October 2008

Out-house Down

The out-house has now been almost completely demolished, just some of the floor and little bits of the walls remaining:





Also, here is the gap for a velux window that will be going in to throw some more light into the kitchen. The ceiling wont be vaulted, so it will be like a light tunnel type effect:

Tuesday, 21 October 2008

One Up One Down

The new roof is going up - all the rafters are now in place - and the old roof on the old outbuildings is coming down



Close up on the new roof:



New location for the satellite dish:

Sunday, 19 October 2008

Through the window

This is what the windows look like at the moment



Most of the brick work appears to be done - the roof is going to start going up on monday.

Thursday, 16 October 2008

No more bricks

Most of the bricks have now been laid - the last the vertical row of red bricks across the top of the extension and for the window ledge



Meanwhile, the builders have improved their darts facilities - even with an oche.

Wednesday, 15 October 2008

Mystery Sewer

Found out today that we werent building over a sewer which was pretty obvious even according to the maps that Welsh Water have but who think they are wrong. All a bit of a strange procedure.