Wednesday, 24 December 2008

Hall Floor

This is the 2 part screed that went down in the hallway in preparation for the new floor. As a bonus it made the house warmer

The worktop

It took a while, but it was fitted in the end:







Saturday, 6 December 2008

Fully rendered

The entire back of the house has now been completely re-rendered, together with the boundary wall where the old out houses stood. You can also see the new coping stones on the top of the wall.

Kitchen going in

On thursday, the kitchen arrived and the builders started fitting it. The worktop will not be arriving until just before Christmas, hopefully...

More Floor Screed

The wooden floor arrived on friday. Before it can be put down the whole downstairs has to have a 2 part latex screed over the old floor tiles. So far its gone down in the old kitchen area. Next week it will go down throughout the hall.

Sunday, 30 November 2008

Rendering the back

The outside of the house is being re-rendered

Old door

Inside the extension with the old doorway into the pantry now fully blocked up



Some of the electric sockets have been installed, the rest will be in this week